Thursday, December 8, 2011

Week 17 (5 Dec - 11 Dec) - Construction Issues

Since last update of my blog, There are very less progress in my new house.
Unfortunately a few major construction errors have been found.
I am very unsatisfied with the construction management and progress.
Some of my concerning and request have been raised and sent to the builder.
I will update my blog once these issues have been solved.



Sunday, November 6, 2011

Week 12 (31 Oct - 6 Nov) - Start Doing Brick Wall

Front View

Patio


Inside Garage

Week 11 (24 Oct - 30 Oct) - No progress


There is no progress in this week.













Week 10 (17 Oct - 23 Oct) - No progress

There is not progress in this week.
However some construction errors have been found during site inspection:
In ground level, two drainage points were located from toilet and laundry wrongly to living room and family room.

Saturday, October 15, 2011

Week 9 (10 Oct - 16 Oct 2011) - Internal plumbing and Windows

1 - Construction progress

  •  Internal plumbing has been installed.
  • All windows are in the position.
  • External wall bricks have been delivered to site.


Internal Plumbing



Windows have been placed in the position

Front View

Back View

Internal View - Rumpus


Wall Bricks have been delivered to site



Friday, October 7, 2011

Week 8 (3 Oct - 9 Oct 2011) - Timber Framing in the 2nd Floor

1 - The invoice of the second progress claim was received and will be due next week
2 - The second floor timber frame has been set up.

Front View


Front Patio


Garage


Main Bedroom - Upstairs


Bathroom 1  - Upstairs


Common Room - Upstairs



Saturday, October 1, 2011

Week 7 (26 Sep - 2 Oct 2011) - The first floor timber flame has been set up

Though it was raining time to time, the first floor timber flame had been setup on Friday (30-09-2011)

1 - Front


2 - Entry

3 - Study Room

4 - Dinning Room


5 - Kitchen

6 - Garage

Monday, September 26, 2011

Week 7 - The First Progress Payment

20% of total amount for the first progress payment is due on Tuesday, 26 september 2011.

Saturday, September 24, 2011

Wednesday, September 21, 2011

Week 4 & 5 (5 Sep - 18 Sep 2011) - Piling and Formworks

Week 4 - Piling
The holes for piers started being drilled on Wednesday, 07 Sep 2011. In most of locations, sandstone was encountered. The depths of holes are mostly within 0.75m to 2.5m.
concrete was poured and completed before the end of the day.


Week 5
The formworks for concrete was installed from Wednesday, 14 September 2011.
All reinforcement in the slab were inspected against engineering drawings by myself on Saturday 17.09.11. (satisfactory)


September 17, 2011
The formworks have been ready for concrete slab









Week 2 & 3 (22 Aug - 4 Sep 2011) - Site Levelling

Week 2
The fence for demolition was removed on Wednesday, 24 August 2011
The site was taken over and fenced by Masterton  on Friday 26 August 2011.
Prompt action, well done.



Week 3
Masterton started levelling the site.

September 02, 2011
Land After Levelling



Week 1 (15 Aug - 21 Aug 2011) - Demolition

Demolition of my old house was carried out by CJE, started on Monday, 15 Aug 2011, and completed on next Tuesday 23 Aug 2011.
As I was busy in my office this week, I didn't inspect the all works carefully.
Unfortunately some concrete blocks in a corner of my land were not removed properly.
It will not impact the construction of the new house.However it could leave me some hard works for the landscaping in the future.


Friendly reminding here:  all works must be inspected carefully before making your payment.



August 25, 2011
Land after Demolition