Since last update of my blog, There are very less progress in my new house.
Unfortunately a few major construction errors have been found.
I am very unsatisfied with the construction management and progress.
Some of my concerning and request have been raised and sent to the builder.
I will update my blog once these issues have been solved.
Thursday, December 8, 2011
Sunday, November 6, 2011
Week 10 (17 Oct - 23 Oct) - No progress
There is not progress in this week.
However some construction errors have been found during site inspection:
In ground level, two drainage points were located from toilet and laundry wrongly to living room and family room.
However some construction errors have been found during site inspection:
In ground level, two drainage points were located from toilet and laundry wrongly to living room and family room.
Saturday, October 15, 2011
Week 9 (10 Oct - 16 Oct 2011) - Internal plumbing and Windows
1 - Construction progress
- Internal plumbing has been installed.
- All windows are in the position.
- External wall bricks have been delivered to site.
Internal Plumbing
Windows have been placed in the position
Front View
Back View
Internal View - Rumpus
Wall Bricks have been delivered to site
Friday, October 7, 2011
Week 8 (3 Oct - 9 Oct 2011) - Timber Framing in the 2nd Floor
1 - The invoice of the second progress claim was received and will be due next week
2 - The second floor timber frame has been set up.
2 - The second floor timber frame has been set up.
Front View
Front Patio
Garage
Main Bedroom - Upstairs
Bathroom 1 - Upstairs
Common Room - Upstairs
Saturday, October 1, 2011
Week 7 (26 Sep - 2 Oct 2011) - The first floor timber flame has been set up
Monday, September 26, 2011
Week 7 - The First Progress Payment
20% of total amount for the first progress payment is due on Tuesday, 26 september 2011.
Saturday, September 24, 2011
Wednesday, September 21, 2011
Week 4 & 5 (5 Sep - 18 Sep 2011) - Piling and Formworks
Week 4 - Piling
The holes for piers started being drilled on Wednesday, 07 Sep 2011. In most of locations, sandstone was encountered. The depths of holes are mostly within 0.75m to 2.5m.
concrete was poured and completed before the end of the day.
Week 5
The formworks for concrete was installed from Wednesday, 14 September 2011.
All reinforcement in the slab were inspected against engineering drawings by myself on Saturday 17.09.11. (satisfactory)
September 17, 2011
The formworks have been ready for concrete slab
The holes for piers started being drilled on Wednesday, 07 Sep 2011. In most of locations, sandstone was encountered. The depths of holes are mostly within 0.75m to 2.5m.
concrete was poured and completed before the end of the day.
Week 5
The formworks for concrete was installed from Wednesday, 14 September 2011.
All reinforcement in the slab were inspected against engineering drawings by myself on Saturday 17.09.11. (satisfactory)
September 17, 2011
The formworks have been ready for concrete slab
Week 2 & 3 (22 Aug - 4 Sep 2011) - Site Levelling
Week 2
The fence for demolition was removed on Wednesday, 24 August 2011
The site was taken over and fenced by Masterton on Friday 26 August 2011.
Prompt action, well done.
Week 3
Masterton started levelling the site.
September 02, 2011
Land After Levelling
The fence for demolition was removed on Wednesday, 24 August 2011
The site was taken over and fenced by Masterton on Friday 26 August 2011.
Prompt action, well done.
Week 3
Masterton started levelling the site.
September 02, 2011
Land After Levelling
Week 1 (15 Aug - 21 Aug 2011) - Demolition
Demolition of my old house was carried out by CJE, started on Monday, 15 Aug 2011, and completed on next Tuesday 23 Aug 2011.
As I was busy in my office this week, I didn't inspect the all works carefully.
Unfortunately some concrete blocks in a corner of my land were not removed properly.
It will not impact the construction of the new house.However it could leave me some hard works for the landscaping in the future.
Friendly reminding here: all works must be inspected carefully before making your payment.
August 25, 2011
Land after Demolition
As I was busy in my office this week, I didn't inspect the all works carefully.
Unfortunately some concrete blocks in a corner of my land were not removed properly.
It will not impact the construction of the new house.However it could leave me some hard works for the landscaping in the future.
Friendly reminding here: all works must be inspected carefully before making your payment.
August 25, 2011
Land after Demolition