Monday, September 26, 2011

Week 7 - The First Progress Payment

20% of total amount for the first progress payment is due on Tuesday, 26 september 2011.

Saturday, September 24, 2011

Week 6 (19 Sep - 25 Sep 2011) - Concrete Slab Completed

Concrete was poured on Monday, 19-09-2011.


Concrete Slab Completed 24-09-2011


Wednesday, September 21, 2011

Week 4 & 5 (5 Sep - 18 Sep 2011) - Piling and Formworks

Week 4 - Piling
The holes for piers started being drilled on Wednesday, 07 Sep 2011. In most of locations, sandstone was encountered. The depths of holes are mostly within 0.75m to 2.5m.
concrete was poured and completed before the end of the day.


Week 5
The formworks for concrete was installed from Wednesday, 14 September 2011.
All reinforcement in the slab were inspected against engineering drawings by myself on Saturday 17.09.11. (satisfactory)


September 17, 2011
The formworks have been ready for concrete slab









Week 2 & 3 (22 Aug - 4 Sep 2011) - Site Levelling

Week 2
The fence for demolition was removed on Wednesday, 24 August 2011
The site was taken over and fenced by Masterton  on Friday 26 August 2011.
Prompt action, well done.



Week 3
Masterton started levelling the site.

September 02, 2011
Land After Levelling



Week 1 (15 Aug - 21 Aug 2011) - Demolition

Demolition of my old house was carried out by CJE, started on Monday, 15 Aug 2011, and completed on next Tuesday 23 Aug 2011.
As I was busy in my office this week, I didn't inspect the all works carefully.
Unfortunately some concrete blocks in a corner of my land were not removed properly.
It will not impact the construction of the new house.However it could leave me some hard works for the landscaping in the future.


Friendly reminding here:  all works must be inspected carefully before making your payment.



August 25, 2011
Land after Demolition