Monday, September 26, 2011
Week 7 - The First Progress Payment
20% of total amount for the first progress payment is due on Tuesday, 26 september 2011.
Saturday, September 24, 2011
Wednesday, September 21, 2011
Week 4 & 5 (5 Sep - 18 Sep 2011) - Piling and Formworks
Week 4 - Piling
The holes for piers started being drilled on Wednesday, 07 Sep 2011. In most of locations, sandstone was encountered. The depths of holes are mostly within 0.75m to 2.5m.
concrete was poured and completed before the end of the day.
Week 5
The formworks for concrete was installed from Wednesday, 14 September 2011.
All reinforcement in the slab were inspected against engineering drawings by myself on Saturday 17.09.11. (satisfactory)
September 17, 2011
The formworks have been ready for concrete slab
The holes for piers started being drilled on Wednesday, 07 Sep 2011. In most of locations, sandstone was encountered. The depths of holes are mostly within 0.75m to 2.5m.
concrete was poured and completed before the end of the day.
Week 5
The formworks for concrete was installed from Wednesday, 14 September 2011.
All reinforcement in the slab were inspected against engineering drawings by myself on Saturday 17.09.11. (satisfactory)
September 17, 2011
The formworks have been ready for concrete slab
Week 2 & 3 (22 Aug - 4 Sep 2011) - Site Levelling
Week 2
The fence for demolition was removed on Wednesday, 24 August 2011
The site was taken over and fenced by Masterton on Friday 26 August 2011.
Prompt action, well done.
Week 3
Masterton started levelling the site.
September 02, 2011
Land After Levelling
The fence for demolition was removed on Wednesday, 24 August 2011
The site was taken over and fenced by Masterton on Friday 26 August 2011.
Prompt action, well done.
Week 3
Masterton started levelling the site.
September 02, 2011
Land After Levelling
Week 1 (15 Aug - 21 Aug 2011) - Demolition
Demolition of my old house was carried out by CJE, started on Monday, 15 Aug 2011, and completed on next Tuesday 23 Aug 2011.
As I was busy in my office this week, I didn't inspect the all works carefully.
Unfortunately some concrete blocks in a corner of my land were not removed properly.
It will not impact the construction of the new house.However it could leave me some hard works for the landscaping in the future.
Friendly reminding here: all works must be inspected carefully before making your payment.
August 25, 2011
Land after Demolition
As I was busy in my office this week, I didn't inspect the all works carefully.
Unfortunately some concrete blocks in a corner of my land were not removed properly.
It will not impact the construction of the new house.However it could leave me some hard works for the landscaping in the future.
Friendly reminding here: all works must be inspected carefully before making your payment.
August 25, 2011
Land after Demolition
Subscribe to:
Posts (Atom)