Monday, February 27, 2012

Week 28 (20.02.12 - 26.02.12) Internal Gyprock wall

1 - Internal gyprock wall was installed.
2 - Internal stair was installed.















Sunday, February 19, 2012

Week 26 (6 Feb - 12 Feb) & Week 27 (13 Feb - 19 Feb)

1 - Roof was completed
2 - Insulation was filled in the wall
3 - Patio was completed.











Sunday, February 12, 2012

Week 24 (23 - 29 Jan 2012) & Week 25 ( 30 Jan - 5 Feb 2012)

No progress.
Comparing with new buildings carried out by other builders, my construction seems too slow.
The Masterton's management need to be improved.
I received claim for the extension of 2 weeks due to rain from Masterton.
I would issue a letter to Masterton that I may refuse this claim unless more sufficient proof provided.