Front View
Hallway
Kitchen
En Suite
Main Bathroom
Double Garage
1 - Kitchen was installed
2 - Painting completed
3 - Start works for bathrooms.
4 - Garage doors were installed.
Finally the doors have been installed.
The house is being locked up. No pictures available.
1 - Internal gyprock wall was installed.
2 - Internal stair was installed.
1 - Roof was completed
2 - Insulation was filled in the wall
3 - Patio was completed.
No progress.
Comparing with new buildings carried out by other builders, my construction seems too slow.
The Masterton's management need to be improved.
I received claim for the extension of 2 weeks due to rain from Masterton.
I would issue a letter to Masterton that I may refuse this claim unless more sufficient proof provided.
Construction guys came back to the site this week after break.
1 - External wall has been cleaned with high-pressure water.
2 - Internal ducts for air-conditioner were installed
3 - Roof tiles and eaves in main building completed.
4 - Outdoor TV antenna was installed.