Saturday, March 24, 2012

Week 32 (19 March - 25 March 2012) - Internal works

Front View




Hallway


Kitchen


En Suite


Main Bathroom


Double Garage

Sunday, March 18, 2012

Week 30 (05 - 11 March) & Week 31 (12 - 18 March)

1 - Kitchen was installed


2 - Painting completed


3 - Start works for bathrooms.


4 - Garage doors were installed.



Sunday, March 4, 2012

Week 29 (28.02.12 - 04.03.12) Finally We have doors.



Finally the doors have been installed.


The house is being locked up. No pictures available.





Monday, February 27, 2012

Sunday, February 19, 2012

Week 26 (6 Feb - 12 Feb) & Week 27 (13 Feb - 19 Feb)

1 - Roof was completed
2 - Insulation was filled in the wall
3 - Patio was completed.











Sunday, February 12, 2012

Week 24 (23 - 29 Jan 2012) & Week 25 ( 30 Jan - 5 Feb 2012)

No progress.
Comparing with new buildings carried out by other builders, my construction seems too slow.
The Masterton's management need to be improved.
I received claim for the extension of 2 weeks due to rain from Masterton.
I would issue a letter to Masterton that I may refuse this claim unless more sufficient proof provided.

Saturday, January 21, 2012

Week 23 (16 Jan - 23 Jan 2012)

Construction guys came back to the site this week after break.
1 - External wall has been cleaned with high-pressure water.
2 - Internal ducts for air-conditioner were installed
3 - Roof tiles and eaves in main building completed.
4 - Outdoor TV antenna was installed.