Building My Own House
Sunday, November 6, 2011
Week 12 (31 Oct - 6 Nov) - Start Doing Brick Wall
Front View
Patio
Inside Garage
Week 11 (24 Oct - 30 Oct) - No progress
There is no progress in this week.
Week 10 (17 Oct - 23 Oct) - No progress
There is not progress in this week.
However some construction errors have been found during site inspection:
In ground level, two drainage points were located from toilet and laundry wrongly to living room and family room.
Saturday, October 15, 2011
Week 9 (10 Oct - 16 Oct 2011) - Internal plumbing and Windows
1 - Construction progress
Internal plumbing has been installed.
All windows are in the position.
External wall bricks have been delivered to site.
Internal Plumbing
Windows have been placed in the position
Front View
Back View
Internal View - Rumpus
Wall Bricks have been delivered to site
Friday, October 7, 2011
Week 8 (3 Oct - 9 Oct 2011) - Timber Framing in the 2nd Floor
1 - The invoice of the second progress claim was received and will be due next week
2 - The second floor timber frame has been set up.
Front View
Front Patio
Garage
Main Bedroom - Upstairs
Bathroom 1 - Upstairs
Common Room - Upstairs
Saturday, October 1, 2011
Week 7 (26 Sep - 2 Oct 2011) - The first floor timber flame has been set up
Though it was raining time to time, the first floor timber flame had been setup on Friday (30-09-2011)
1 - Front
2 - Entry
3 - Study Room
4 - Dinning Room
5 - Kitchen
6 - Garage
Monday, September 26, 2011
Week 7 - The First Progress Payment
20% of total amount for the first progress payment is due on Tuesday, 26 september 2011.