- PCI completed
- Final inspection completed
- A few of deviations to be fixed
- Handover is scheduled next week
- Solid timber floor will be arranged by ourselves and installed in both ground and top levels starting from end of next week.
- A few landscaping guys have been invited to provided quotation.
Saturday, April 14, 2012
Saturday, March 24, 2012
Sunday, March 18, 2012
Week 30 (05 - 11 March) & Week 31 (12 - 18 March)
1 - Kitchen was installed
2 - Painting completed
3 - Start works for bathrooms.
4 - Garage doors were installed.
2 - Painting completed
3 - Start works for bathrooms.
4 - Garage doors were installed.
Sunday, March 4, 2012
Week 29 (28.02.12 - 04.03.12) Finally We have doors.
Finally the doors have been installed.
The house is being locked up. No pictures available.
Monday, February 27, 2012
Sunday, February 19, 2012
Sunday, February 12, 2012
Week 24 (23 - 29 Jan 2012) & Week 25 ( 30 Jan - 5 Feb 2012)
No progress.
Comparing with new buildings carried out by other builders, my construction seems too slow.
The Masterton's management need to be improved.
I received claim for the extension of 2 weeks due to rain from Masterton.
I would issue a letter to Masterton that I may refuse this claim unless more sufficient proof provided.
Comparing with new buildings carried out by other builders, my construction seems too slow.
The Masterton's management need to be improved.
I received claim for the extension of 2 weeks due to rain from Masterton.
I would issue a letter to Masterton that I may refuse this claim unless more sufficient proof provided.