Wednesday, September 21, 2011

Week 2 & 3 (22 Aug - 4 Sep 2011) - Site Levelling

Week 2
The fence for demolition was removed on Wednesday, 24 August 2011
The site was taken over and fenced by Masterton  on Friday 26 August 2011.
Prompt action, well done.



Week 3
Masterton started levelling the site.

September 02, 2011
Land After Levelling



No comments:

Post a Comment