Week 24 (23 - 29 Jan 2012) & Week 25 ( 30 Jan - 5 Feb 2012)

No progress.
Comparing with new buildings carried out by other builders, my construction seems too slow.
The Masterton's management need to be improved.
I received claim for the extension of 2 weeks due to rain from Masterton.
I would issue a letter to Masterton that I may refuse this claim unless more sufficient proof provided.